Please purchase a subscription to read our premium content. If you have a subscription, please log in or sign up for an account on our website to continue.
Please log in, or sign up for a new account to continue reading.
Thank you for reading! We hope that you continue to enjoy our free content.
Welcome! We hope that you enjoy our free content.
Thank you for reading! On your next view you will be asked to log in to your subscriber account or create an account and subscribe purchase a subscription to continue reading.
Thank you for reading! On your next view you will be asked to log in to your subscriber account or create an account and subscribe purchase a subscription to continue reading.
Thank you for signing in! We hope that you continue to enjoy our free content.
Please purchase a subscription to read our premium content. If you have a subscription, please log in or sign up for an account on our website to continue.
Your current subscription does not provide access to this content.
Already a subscriber on our previous website? Connect with your last name & phone number
Sorry, no promotional deals were found matching that code.
Promotional Rates were found for your code.
Klickitat PUD is starting to experience critical electric system equipment shortages due to the global shortage of materials and longer delivery delays from many vendors.
Jim Smith, KPUD general manager, said that with material delivery delays and increased construction volumes, the utility is short on stock for their standard pad mounted transformers. These transformers take high voltage power from the PUD’s distribution lines and convert it to the 120 and 240 volts delivered to residences and businesses when underground power lines are used. Transformers are on order and the PUD expects deliveries throughout the year.
“We have been communicating with new customers and developers for months that we were expecting these shortages,” said Smith. “Existing customers should also realize that we are facing the same supply chain issues that they are seeing in stores. Delivery times are getting longer, and prices are increasing across many materials.”
“For example, these transformers normally have about a 16-week delivery time and were $1,500 each a year ago. Delivery is now more than a year out and they are being quoted at $6,000 each,” said Smith.
Compounding the supply chain problem is a large increase in new construction in Klickitat County. The PUD would normally see about $1.4 million in new electric construction activity each year. In 2021, this increased to $2.8 million and the same is expected for 2022.
At this time, KPUD and the electric industry are seeing the supply chain shortages limited to transformers. However, this combination of supply shortages, longer delivery times and increased construction may cause additional shortages in other utility equipment. PUD staff has been working to source materials for these elevated construction levels for 2022 and for the 2023 construction season as well.
“The PUD Commissioners have directed staff to commit the funds required to allow us to keep two years of inventory in stock, rather than the normal six to twelve months,” said Smith. “We have the funds to be able to acquire these additional materials to support the increased growth in the county, but with limited supply and elevated usage, there is only so much we can do”.
If you have questions or interest in new developments and want to know more about the impacts these material issues could have, contact the PUD engineering department.